Well my buddy and I got a 1990 Cutter Classic 158...is a 15' bowrider..the hull is in pretty good shape...the floor was "spongy"...so we knew it needed to be replaced. We had originally hoped to only replace a small section...but once we removed the carpet...it was obvious..we needed to remove more. We have completed one days work. Any advice or opinions...please let me know!
DAY 1
- Removed carpet
- Cut Fiberglass mat at rotted plywood's edge and removed all plywood
Before Floor removal
Cabin view before floor removal
Cutting out Floor
Stern view with floor removed
Bow view with floor removed
Again, any advice is appreciated as tomorrow we will begin the process of building the floor. Here is our plan:
- Build floor using pressure treated plywood and stainless steel screws
- Epoxy all ends and fiberglass top and sides
Well start it anyways...doubt we will get those 2 steps all done tomorrow.
DAY 1
- Removed carpet
- Cut Fiberglass mat at rotted plywood's edge and removed all plywood
Before Floor removal

Cabin view before floor removal

Cutting out Floor

Stern view with floor removed

Bow view with floor removed

Again, any advice is appreciated as tomorrow we will begin the process of building the floor. Here is our plan:
- Build floor using pressure treated plywood and stainless steel screws
- Epoxy all ends and fiberglass top and sides
Well start it anyways...doubt we will get those 2 steps all done tomorrow.