Working on more cutting out old fiberglass & wood and performing inspections.
Now that I have the vast majority of the floor out, I'm looking hard at the stringers & motor mounts.
I'm certain that I have some replacement to do at least on the rear (stern) half of the stringers. The fiberglass was dis-bonded from the stringers and motor mounts around the bilge area. Now that I'm cutting that away, I'm seeing all of the rot in the stringers back there. Pictures are attached.
The motor mount main timbers (looks like 6x6, see pictures) are also significantly rotted. I really don't like how they are made anyway with a piece of 2x4 on top of the timber to allow additional height for the motor mount. Plus, the motor mount lag bolts are in there crooked.
I've already had some discussion in this thread about the fuel tank compartment (forward of the bilge). Since I'm pretty sure I'm going to be replacing the fuel tank, I'm going to need to widen out the stringers there a bit to allow for some extra clearance for a new tank. Seems most new poly tanks are needing more room than I had in there. Even the old one shows signs that it was too tight in the area. I'm going to be sketching up some new stringer layouts in the near future and will share them.
Here is a picture of the stringers going forward from the fuel tank compartment through the ski locker area. These all look solid so far. The only exception is where the bulkheads attached (you can see the two spots in the picture. The bulkheads were notched into the stringers and weren't encapsulated fully with fiberglass. I have to look at these areas more closely to make sure there's no rot there. Since I'm going to be replacing the aft half of the stringers, I may go ahead and replace these too. I don't like how they were notched for the bulkheads and they don't look like they would be too difficult to replace.