Hello all, new to the forum. Just getting back into boating after being out for several years and just purchased a '06 Regal 2000. I also recently moved to a home with a boat lift and have a question about it.
The width between my pilings is 9'. The lift cradle is 8.1' between cables. The beam of my boat is 8.6'
I was originally planning on having some extension brackets welded onto the existing I-beams as an alternative to having to replace them since they are still in good condition, which would allow me to move the cables out several inches on each side to not stretch them when moving the boat in and out. However, others are telling me that there is not enough room to put on extensions because the cradle itself needs to be able to move with the boat (side to side) instead of being closer up against the pilings. The other alternative is to add another pulley on each of the pilings, leave the cable attached where it is and run it at an angle of something like 40 degrees up to the pulley which will then allow the cable to run agains the piling up to the top. The only concern over this is that the angle at which the cable would have to go up to reach the pulley may still hit the side of the boat and I would prefer it not to be rubbing against the hull! Besides the width of the pulley is also going to take up room and could possibly rub against the side of the boat if it was to swing when the boat is raised.
Unfortunately having new pilings installed is not possible as I would also have to completely redo the roof of which all is just not in the budget.
I know its a semi-tight fit, but wonder if anyone would have any advice on the best way to proceed for the time being? Is it really a bad idea to weld on extensions to bring the beam within only an inch or so of the piling or would it still be better to just go with the angle and pulley option?
Thanks all!
The width between my pilings is 9'. The lift cradle is 8.1' between cables. The beam of my boat is 8.6'
I was originally planning on having some extension brackets welded onto the existing I-beams as an alternative to having to replace them since they are still in good condition, which would allow me to move the cables out several inches on each side to not stretch them when moving the boat in and out. However, others are telling me that there is not enough room to put on extensions because the cradle itself needs to be able to move with the boat (side to side) instead of being closer up against the pilings. The other alternative is to add another pulley on each of the pilings, leave the cable attached where it is and run it at an angle of something like 40 degrees up to the pulley which will then allow the cable to run agains the piling up to the top. The only concern over this is that the angle at which the cable would have to go up to reach the pulley may still hit the side of the boat and I would prefer it not to be rubbing against the hull! Besides the width of the pulley is also going to take up room and could possibly rub against the side of the boat if it was to swing when the boat is raised.
Unfortunately having new pilings installed is not possible as I would also have to completely redo the roof of which all is just not in the budget.
I know its a semi-tight fit, but wonder if anyone would have any advice on the best way to proceed for the time being? Is it really a bad idea to weld on extensions to bring the beam within only an inch or so of the piling or would it still be better to just go with the angle and pulley option?
Thanks all!