Re: PROJECT ~ JEZABEL 23' Sleekcraft Executive ~TO Do LIST
Re: PROJECT ~ JEZABEL 23' Sleekcraft Executive ~TO Do LIST
Well, heres the TO DO list...............I'll double post this on the 1rst posting of this thread maybye later...and check em off as completed!. Last update OCT 3rd 2009 1pm PST 2009
Must Do's or WANT to do's - GREEN indicates complete...Red needs to be done! before sea trials.............. Yellow is work in progress
-------
BILGE / ENGINE
Clean and re-paint engine, polish chrome and exhaust
COMPLETED
Replace all rubber hoses on engine COMPLETED
Compression test engine add marvel mystery oil to each cylinder before startup, replace spark plugs
COMPLETED
Rebuild carb...adjust carb COMPLETED
Check ignition timing <>
BILGE - fix holes that we drilled to air out the pinhole leak in the frt of the bilge separator plate (frt of bilge)
COMPLETED
BILGE - remove prev owner installed jerry rigged drain hole ...will post pic of that one! also found a screw blocking a hole, fixed that while in there (back of transom)
COMPLETED
BILGE - add second NEW bilge pump <may not do that>
BILGE - replace old bilge pump hose it is swellled a bit...
COMPLETED but with a snag!
BILGE Install new bilge exit port (3/4") prev owner had 3/4 inch hose clamped down onto 1/2" fitting! nice having bilge water come back ini the boat when it leaks eh?
COMPLETED drilled bigger hole...replaced bilge exit port with 3/4" new fitting
BILGE - old bilge pump clean and test (it's the cartridge kind and is epoxied in) -
COMPLETED / WORKS
BILGE - Gel coat entire bilge area! or paint it since we started doing that.
COMPLETED (painted it aluminum)
BILGE - oil bilge blower and re-test or REPLACE bilge blower
COMPLETED replaced with new atwood inline turbo
-----------
STERNDRIVE
Sterndrive - Test trim/lift hydraulics -
COMPLETE / WORKS but has leak!
Sterndrive - Found leak at port trim cylinder! need a reseal kit or replace BOTH cylinders I will check it off = once I look into it or fix it<>
Sterndrive - Order NEW upper housing, Starboard trim sensor, orings & gaskets & recieve parts -
COMPLETED
Sterndrive - Replace upper housing, inspect guts, replace seals, re-assemble upper unit, mate to lower unit -
current work in progress
Sterndrive - Strip and paint sterndrive and transom plate, gimbal Chrysler White! the ol' WHITE ANCHOR!!!! lol

<
Got it all tore down and stripped, might paint today but 25 mph winds are called for (dust and sand)>
-----------
INTERIOR
Strip out old interior[/B] and chocolate colored carpeting BARF!!
COMPLETED
Manufacture new captains seat base / cooler stowage
COMPLETED
Cover new seat base with scrap vinyl from prev project, paint with tan vinyl paint
COMPLETED
Engine box / jump seats Recover vinyl as needed, paint to match using vinyl paint
COMPLETED
Engine box / jump seats Install into boat / bolt in place
COMPLETED
go out and eat mexican food [/B]in celebration of interior work done YEA!
COMPLETED
-----------
TRAILER
Replace blown tire <>
Grease and inspect all wheel bearings <>
Replace all wheel seals <>
add bearing buddies <>
Check trailer brake pads <>
Double check trailer lighting <>
---------
COSMETICS
Poli-glow gelcoat restore the entire hull -
COMPLETED looks awsome I-Boats should carry this product!
Make wood lattice for deck drop down area (I want a flat deck) <>
Polish trailer wheels <>
Prep / Prime / Paint the whole trailer! <Got the paint the other day!>
Replace Bunk Carpeting <>
Repair a couple exterior gel coat chips and dings near transom
<work in progress repaired all the dings and scrapes, holes....faired it all in ..have to sand the new gel coat down and polish it>
---------
LEGAL STUFF
DMV title for trailer / out of state inspection of trailer / license plate <>
DOW boat title and tag <>
BOAT TAGS = Lake Mead Natl Rec area FEE AREA! need the OTHER tag for the boat <>
Make sure all safety equipment on board and
TEST HER OUT on the water! <>